The Fukushima Experimental Offshore Wind Farm Project

Experimental Offshore Wind Farm
Fukushima 7 mwatt offshore floating wind turbine project and experiment

Japan Builds an Experimental Offshore Wind Farm Project – As a result of the Fukushima nuclear disaster and ongoing clean up and containment efforts with that site Japan has greatly reduced their present and future commitment to Nuclear energy. In fact they are pursuing all forms of clean energy including solar and offshore wind. This project is a very ambitious offshore multiple wind turbine platform prototype under development.

Project Update for Phase 2 of the Offshore Wind Project

A consortium comprised of Marubeni (project integrator), the University of Tokyo (technical advisor), Mitsubishi, Mitsubishi Heavy Industries, Japan Marine United, Mitsui Engineering & Shipbuilding, Nippon Steel & Sumitomo Metal Corporation, Hitachi, Furukawa Electric, Shimizu, and Mizuho Information & Research, has been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012. Here are some pictures thanks to Hitachi

Floating wind turbine experiment to replace nuclear in Japan

Floating wind turbine experiment to replace nuclear in Japan. Picture credit Hitachi

Preparatory works for the installation of the 7MW oil pressure drive-type wind turbine on the three-column semi-sub floater at Onahama port, Fukushima, are almost completed and delivery of the floater from Nagasaki to Onahama has started today as part of the second term.

The downwind type floating offshore wind turbine

The downwind type floating offshore wind turbine. Photo credit Hitachi

1. Outline of construction works in the second term:

Assembly and setting of two units of the 7MW oil pressure drive-type floating wind turbines, delivery of the facilities to the testing area, and connection to the undersea cable.

2. Work progress to date:

7MW oil pressure drive-type floating wind turbine

Floater

  • Delivery of the three-column semi-sub floater from Nagasaki to Onahama port is in progress.

Wind Turbine

  • Construction of the nacelle for the 7MW oil pressure drive-type wind turbine is in progress at Mitsubishi Heavy Industries, Ltd. Yokohama Dockyard & Machinery Works.
  • Construction of the tower for 7MW oil pressure drive-type floating wind turbine is in progress at Mitsubishi Heavy Industries, Ltd. Kobe Dockyard & Machinery Works.

Mooring System & Undersea cables

  • Preceding works i.e. installation of chains, anchors and undersea cables at the testing area has been successfully completed.

Port improvement for 7MW turbine installation

  • Ground improvement and installation of the undersea mound at Onahama port for mounting the wind turbine on the three-column semi-sub has been successfully completed.
Japan experiments with offshore wind energy to make up for Nuclear

Japan experiments with offshore wind energy to make up for Nuclear

3. Next Step

The following activities need to be completed to start operation of the power facilities:

* Schedule will be changed depending on the meteorological and sea conditions

November 10 Arrival of the three-column semi-sub floater and mounting at Fujiwara quay, Onahama port
Late November – Late January Assembly of a large-scale crane at Onahama port for the purpose of the installation work
Early February – Installation of the 7MW oil pressure drive-type wind turbine on the three-column semi-sub floater, delivery of the facility and its mooring operation in the testing area